Project update: Harryville
The houses at Wakehurst Court are due for handover on the 5th, 9th and 18th of September, with all ground works on site complete.
Apartment Blocks 1 and 2 are complete with just minor snagging to be done.
The full development is due to be handed over to Clanmil Housing on the 19th of September, a total of 48 homes.