Progress Update: Derry’s, Plymouth Cross

Progress continues at Derry’s, Plymouth Cross with the remodelling, extending and refurbishment of the existing 292,000 sq ft structure as well as adding a top-floor hotel.

Summary of works completed in February: 2019

  • Out of the ground completed; Piles/Concrete/Pads.
  • Existing Sub Station and J9 waterproofing completed.
  • Demo core 2 & 4 complete and next phase of scaffold erection.
  • Rear of Riley’s Core 6 Demo works complete and removal of crash deck.
  • Hoarding moved to allow WPD access.
  • Tarmac at the new substation and jet washing to exterior are complete.

Feb 19 - Progress: Plymouth Feb '19

Core 6 Feb 2019 e1551440858611 - Progress: Plymouth Feb '19

16199 Plymouth 4 1 750x500 - Progress: Plymouth Feb '19

Summary of programmed activities in the next month (March 2019):

  • Final 2% demo from completion
  • Concrete removal continues – 90% completed
  • Ground works on rear of Riley’s and Retail units
  • Pod deliveries continue
  • M&E works continue
  • Steel complete in Core 6
  • Stairs arrive Core 6
  • Steel starts in Core 2
  • Steel ordered Core 2
  • Argos loading bay planed works
  • Façade sub to be appointed
  • BC to start the hoarding move
  • Plasterers to be appointed for Unit 11 & Retail
  • Painters to be appointed for Unit 11 & Retail
  • Joiner for door linings Unit 11 & Retail
  • Remove damaged walls in basement and replace (stud)

Watch out for more updates.